FERC begins pre-filing environmental review of Great Basin Gas Transmission’s 2028 Expansion Project, including 195 mi of 42-in. pipe in Nevada.
Federal Energy Regulatory Commission (FERC) staff will prepare an environmental document for Great Basin Gas Transmission Company’s 2028 Expansion Project, a proposal to build about 195 mi of new 42-in.-diameter natural gas pipeline across northern Nevada while retiring roughly 142 mi of mostly 1960s-era line.
The review is taking place under FERC’s pre-filing process, meaning Great Basin has not yet filed a formal application. The Commission will use the environmental document to help determine whether the project is in the public convenience and necessity.
Project scope
The 2028 Expansion Project would span Churchill, Humboldt, Lyon, Pershing, Storey and Washoe counties. In addition to the 42-in. mainline, Great Basin plans approximately 15 miles of new 24-inch-diameter lateral pipelines and would construct and operate:
·      The new Jungo Road Compressor Station in Humboldt County
·      A new receipt point adjacent to Great Basin’s existing Opal Valley Receipt Point
·      New delivery points, meter stations, pressure limiting stations and other appurtenant facilities.
The project also calls for abandoning about 142 mi of existing 8- and 16-in.-diameter pipeline, most of it built in the 1960s, along with the existing Rye Patch and Lovelock compressor stations.
Construction and abandonment activities would disturb a preliminary estimate of 4,500 acres. Great Basin would retain about 1,500 acres for permanent operation of the facilities, with the remaining land restored to its former uses. FERC said most of the pipeline facilities would be collocated with existing pipeline, utility and road rights-of-way (ROW).
The environmental document will assess impacts on geology and soils, water resources and wetlands, vegetation and wildlife, threatened and endangered species, cultural resources, land use, socioeconomics, air quality and noise, and reliability and safety.
Based on a preliminary review of the planned facilities and Great Basin’s environmental information, Commission staff identified several issues for particular attention:
·      Public land crossings and recreational land use
·      The California National Historic Trail
·      Protected species
·      Air quality, noise and visual impacts from proposed new aboveground facilities
·      Waterbody crossings, including the Humboldt River and various canals
·      The proposed abandonment of an older pipeline in place.
FERC noted the list may change based on public comments and further analysis. Staff will also evaluate reasonable alternatives to all or part of the project and recommend measures to reduce or avoid impacts.
FERC’s pre-filing process is intended to encourage early stakeholder involvement and to identify and resolve issues before an application reaches the Commission. As part of the review, Commission staff will contact federal and state agencies to discuss their roles in scoping and in preparing the environmental document.