FERC sets June 2027 target for final order on Guardian 3 Expansion Project

The Federal Energy Regulatory Commission (FERC) expects to issue a final order on Guardian Pipeline LLC’s proposed Guardian 3 Expansion Project no later than June 17, 2027, according to a notice establishing the environmental review schedule for the Illinois and Wisconsin natural gas project.

The Federal Energy Regulatory Commission (FERC) expects to issue a final order on Guardian Pipeline LLC’s proposed Guardian 3 Expansion Project no later than June 17, 2027, according to a notice establishing the environmental review schedule for the Illinois and Wisconsin natural gas project.

Commission staff will prepare an environmental assessment (EA) for the project, which FERC plans to issue on March 5, 2027, followed by a 30-day public comment period. Other federal agencies with permitting roles face a June 3, 2027, deadline to reach decisions on their authorizations, 90 days after the EA’s release.

Guardian filed its application on July 1, 2026, in Docket No. CP26-548-000, seeking a certificate of public convenience and necessity under Section 7(c) of the Natural Gas Act. The project would provide about 536,903 dekatherms per day (Dth/d) of long-term firm transportation capacity to help meet rising natural gas demand in Wisconsin and neighboring states.

Project scope

The expansion centers on roughly 68 mi of new 36-inch-diameter looping pipeline in northern Illinois, along with added compression in both states. Proposed facilities include:

·       Juliet Loop: approximately 42.6 mi of 36-inch looping pipeline in Kendall and DeKalb counties, Illinois

·       Sycamore Loop: approximately 25.5 mi of 36-inch looping pipeline in DeKalb and McHenry counties, Illinois

·       Joliet Compressor Station: two new 11,110-horsepower (hp) compressor units at Guardian’s existing station in Will County, Illinois

·       Sycamore Compressor Station: modifications to compression facilities at the existing station in DeKalb County, Illinois

·       Eden Compressor Station: a new greenfield 9,000-hp station in Dodge County, Wisconsin

·       Sheboygan Meter Station: a new greenfield meter and regulator station in Fond du Lac County, Wisconsin

·       Other appurtenant pipeline facilities in Illinois.